SHAMKIR EXCELCIOR HOTEL, Shamkir – AZERBAIJAN, Boutique Hotel & SPA
- Turn-key Design & Construction / Project management was requested by the investor of Qalaalti Hotel & SPA for the 60-room boutique Hotel & SPA in the city of Shamkir (Azerbaijan).
- Design based on given pre-concept has been developed (all disciplines including Interior Design excluding Landscape design) and coordinated in a BIM. In 3 months, all design has been developed, coordinated & tendered.
- After qualification of the contractor based on design development level tender documentation, construction documentation has been started to be delivered for the smooth construction period.
- Turn-key hand over of the hotel has been achieved in 11 months including all design phases, coordination & construction of superstructure, envelope, fit-out & landscape.
- Challenges during the design & construction were deadlines which are very tight, however, all has been achieved via good planning & coordination between the design & construction teams. We at this time, planned all important procurements including SPA, Kitchen, laundry equipment, brewery, elevators, room fit outs & principle MEP equipment. Result & achieved quality were more than satisfactory and superior than all built artefacts which were already build in that city till that time.
BIM VIEWS
INTERIOR DESIGN RENDERS
PHOTOS
RESPONSIBILITY MATRIX
PROGRAM & FEASIBILITY STUDIES ✅ | INVESTOR | |
ARCHITECTURAL | PRE-CONCEPT | TOGRUL RUSLANOGLU |
CONCEPT DESIGN | TOGRUL RUSLANOGLU | |
SCHEMATIC DESIGN ✅ | RENAISSANCE | |
DESIGN DEVELOPMENT ✅ | RENAISSANCE | |
CONSTRUCTION DOCUMENTATION ✅ | RENAISSANCE | |
ENGINEERING | CONCEPT DESIGN ✅ | RENAISSANCE |
SCHEMATIC DESIGN ✅ | RENAISSANCE | |
DESIGN DEVELOPMENT ✅ | RENAISSANCE | |
CONSTRUCTION DOCUMENTATION ✅ | RENAISSANCE | |
TENDER DOCUMENTATION ✅ | RENAISSANCE | |
ARCHITECT OF RECORD ✅ | RENAISSANCE | |
PROJECT MANAGEMENT ✅ | RENAISSANCE | |
DESIGN MANAGEMENT & COORDINATION ✅ | RENAISSANCE | |
SITE SUPERVISION ✅ | RENAISSANCE |